Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module s lecture homework help
In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.
Activity Task Predecessors Duration Activity Cost A Sign Contract None 5 days $5,000 B Design Survey A 3 days $1,500 C Identify Audience A 7 days $1,000 D Run Survey B, C 30 days $6,000 E Analyze Results D 5 days $3,000 F Create Presentation E 5 days $1,000 G Present to Client E, F 2 days $3,000
- Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module’s lecture.
- What is the duration of the project?
- How much slack is currently available in the non-critical path?
- How long are the project and feeder buffers?